Enabling Large-Scale Renewable Energy Infrastructure in the Asir Region
Supporting Saudi Arabia’s renewable energy transition through the construction of a 132 kV Twin Double Circuit Overhead Transmission Line for the Bisha Independent Power Producer (IPP) Solar & Renewables Project.
Project Snapshot
Client
Client ACWA Power / L&T Saudi Arabia
Location
Bisha – Asir Region, Saudi Arabia
Voltage
132 kV Twin D/C
Duration
6 Months
Project Value
SAR 3 Million
Scope
Tower Erection, OPGW Installation & Conductor Stringing
Project Overview
Supporting Saudi Arabia's Renewable Energy Vision
As Saudi Arabia accelerates the development of renewable energy infrastructure under Vision 2030, reliable transmission networks play a critical role in delivering clean energy from generation facilities to the national grid.
Venus Energy successfully executed key transmission infrastructure works for the Bisha IPP Solar & Renewables Project, one of the Kingdom’s large-scale renewable energy developments.
The project involved the construction of a 132 kV Twin Double Circuit Overhead Transmission Line, supporting the evacuation and transmission of power generated from the 3 GW Bisha One Renewable Power Project.
This infrastructure plays an important role in strengthening grid connectivity while supporting the Kingdom’s long-term energy diversification goals.
Project Objectives
Delivering Infrastructure for Clean Energy Integration
Reliable evacuation of renewable energy
Enhanced grid connectivity
Support for Saudi Vision 2030 energy initiatives
Improved power transmission reliability
Long-term renewable energy development
What We Do
SCOPE OF WORK
01
Transmission Infrastructure Execution
Venus Energy successfully executed critical transmission line activities required for the project.
02
Tower Erection
Installation and erection of transmission towers in accordance with project specifications, engineering requirements, and international safety standards.
03
OPGW Installation
Execution of conductor stringing activities to establish transmission connectivity and support power evacuation from the renewable energy facility.
04
Conductor Stringing
Execution of conductor stringing activities to establish transmission connectivity and support power evacuation from the renewable energy facility.
05
Project Coordination
Installation of Optical Ground Wire (OPGW) systems supporting communication, monitoring, and network reliability requirements.
CHALLENGE
Delivering Infrastructure in Extreme Desert Conditions
The project was located within a remote desert environment where extreme temperatures and challenging site conditions required additional planning and operational controls.
In addition to environmental challenges, the project was required to comply with the world-class safety and quality standards established by ACWA Power and L&T Saudi Arabia.
The Venus Solution
Safety-Driven Execution for Successful Project Delivery
An alternative foundation method adopted in rock strata, keeping construction safe, efficient and on programme.
GPS-Based Vehicle Monitoring
GPS tracking systems were installed in project vehicles to improve operational visibility, workforce safety, and movement control across the project site.
Heat Stress Management
To protect workers from extreme temperatures, mandatory midday breaks were implemented between 12:00 PM and 3:00 PM in accordance with project safety requirements.
Workforce Medical Screening
All personnel completed medical fitness assessments before entering the project site, ensuring workforce readiness and compliance with project safety standards.
Successful Execution
Project activities were executed in alignment with the stringent safety and quality systems established by ACWA Power and L&T Saudi Arabia.
Safety-Driven Execution for Successful Project Delivery
Venus Energy implemented a comprehensive project execution strategy focused on workforce safety, operational control, and compliance with client requirements.
Solutions Implemented
Project Impact
Powering Renewable Energy Infrastructure
Powering Renewable Energy Infrastructure
The completed transmission infrastructure now supports one of the Kingdom’s major renewable energy developments.
Renewable Energy Integration
Supporting the transmission of clean energy generated from the Bisha One Renewable Power Project.
Infrastructure Development
Strengthening network connectivity between renewable generation assets and the power grid.
Safety Excellence
Demonstrating the successful implementation of international safety standards within challenging operating environments.
Sustainable Infrastructure Development
Contributing to Saudi Arabia’s long-term renewable energy and sustainability objectives.
Project Gallery
Project Highlights
WHY THIS PROJECT MATTERS
Supporting Saudi Arabia's Clean Energy Future
Saudi Arabia’s renewable energy ambitions require reliable transmission infrastructure capable of integrating large-scale solar generation into the national grid.
This project demonstrates Venus Energy’s ability to deliver transmission infrastructure for utility-scale renewable energy projects while maintaining the highest standards of safety, quality, and operational excellence.
By supporting the Bisha One Renewable Power Project, Venus Energy contributed to the Kingdom’s broader goals of energy diversification, sustainability, and long-term infrastructure development.