Construction of 132 kV Double Circuit Overhead Transmission Line from Al Birk to Al Haredha

Strengthening Power Infrastructure Across the Jizan–Asir Region
Supporting reliable power transmission through the construction of a 132 kV Double Circuit Overhead Transmission Line connecting Al Birk and Al Haredha substations.
Project Snapshot
Client
AlOjaimi
Location
Jizan – Asir Region
Voltage
132 kV D/C
Duration
12 Months
Project Value
SAR 3 Million
Scope
Foundations, Tower Erection & Stringing
Project Snapshot
Client
AlOjaimi
Location
Jizan – Asir Region
Voltage
132 kV D/C
Duration
12 Months
Project Value
SAR 3 Million
Scope
Foundations, Tower Erection & Stringing
Project Overview

Connecting Communities Through Reliable Power Infrastructure

Venus Energy constructed a 132 kV Double Circuit Overhead Transmission Line linking the Al Birk and Al Haredha substations in the Jizan–Asir region of Saudi Arabia. Delivered for AlOjaimi over twelve months, the project covered foundations, tower erection and stringing across demanding coastal and mountain terrain. The line reinforces regional transmission capacity, supporting stable power flow and improved network reliability for communities and industry served by the southern grid.
Project Objectives

Supporting Grid Stability and Network Reliability

Improved Power Flow Stability

A double circuit route that balances load across the regional network.

Enhanced Network Reliability

Redundant circuits reduce interruption risk between substations.

Infrastructure Development

New transmission capacity for growing communities in the south-west.

Long-Term Network Performance

Durable foundations and structures engineered for decades of service.
What We Do

End-to-End Power Infrastructure Solutions

01

Foundation Works

Excavation, reinforcement and casting of tower foundations across mixed soil and hard rock along the route, with open-type foundations adopted where rock conditions demanded it.
02

Tower Erection

Assembly and crane erection of double circuit lattice steel towers, with full alignment, bolt torquing and structural verification at every location.
03

Stringing Works

Tension stringing of conductors and earth wire using controlled pulling equipment, followed by sagging, clipping and accessory installation.
04

Project Execution

Route survey, material logistics, quality control, HSE supervision and utility coordination through to testing, commissioning support and handover.
Start a Conversation

Planning a Transmission or Distribution Project?

“Hard rock formations affected conventional foundation construction methods, requiring an alternative engineering approach.”

The Venus Solution

Engineering Practical Solutions in the Field

Challenge
Hard rock encountered along the alignment.
Assessment
Geotechnical review at each affected location.
Alternative Foundation Method
Open-type foundations designed for rock strata.
Successful Execution

Programme maintained without rework.

Engineering Practical Solutions in the Field

An alternative foundation method adopted in rock strata, keeping construction safe, efficient and on programme.
The Venus Solution
Project Impact

Delivering Infrastructure That Supports Growth

Enhanced Grid Connectivity

A firm 132 kV link between the Al Birk and Al Haredha substations.

Improved Power Flow Stability

Steadier transmission across the Jizan–Asir corridor.

Infrastructure Development

Capacity to support residential, industrial and utility growth.

Long-Term Network Reliability

Assets built to perform through demanding terrain and climate.
Project Gallery

Project Highlights

Where We Create Value

Supporting Critical Infrastructure Across the Kingdom

Reliable transmission is the foundation of national growth, industry and everyday life.

Projects such as the Al Birk to Al Haredha line extend the reach and resilience of the national grid, aligning with the Kingdom’s long-term infrastructure ambitions and the energy needs of a growing population.
Related Projects

Explore More Projects

substation
project
Start a conversation

Planning a Transmission Infrastructure Project?

Partner with a team experienced in delivering reliable power infrastructure solutions across Saudi Arabia.
Scroll to Top